BOWTHORPE UNIT 11 FRANCIS WAY REFURBISHMENT
Location: NORWICH

CLIENT:
INDURENT
‍
‍Project Value: £50,000

We successfully delivered a comprehensive refurbishment and reinstatement project at Unit 11 Francis Way, Bowthorpe Park Industrial Estate, returning the end-of-terrace industrial unit to a high-quality, compliant and market-ready condition.

The project was undertaken following the end of a lease, with works focused on reinstating the unit to Indurent’s standard specification while incorporating key compliance improvements and EPC upgrades. The completed refurbishment has enhanced the overall quality, efficiency and flexibility of the warehouse and office accommodation, providing a modern space ready for future occupation.

PROJECT SCOPE

The refurbishment works were designed to reinstate the unit, improve compliance and enhance the overall condition of the facility. Our works included:

  • Full strip-out of the existing tenant fit-out
  • Internal redecoration of walls and floors throughout the unit
  • Replacement of carpets and vinyl flooring
  • Installation of a new fire alarm system to meet Part M requirements
  • Installation of emergency lighting throughout
  • Complete LED lighting upgrade across the building
  • EPC improvement works, including installation of air conditioning to office areas
  • Removal of the existing gas supply
  • Delivery of landlord compliance and white box works

The project was delivered under a JCT Minor Works Contract over a three-week programme, with careful planning and coordination ensuring the refurbishment was completed efficiently and ready for future occupation.

PROJECT HIGHLIGHTS

Landlord ComplianceThe refurbishment successfully brought the unit in line with Indurent’s required standards, incorporating essential compliance works and improvements to building systems.

EPC ImprovementsEnergy efficiency was enhanced through targeted upgrades, including improved lighting systems and the installation of air conditioning within the office accommodation.

Complete ReinstatementThe existing tenant fit-out was removed and the unit was returned to a clean, flexible condition suitable for a range of future occupiers.

Efficient Delivery Working within a short three-week programme, we carefully coordinated all activities to complete the works safely, efficiently and to the required specification.

Market-Ready Solution The completed refurbishment has provided a modern, compliant and adaptable industrial unit, improving its appeal and readiness for future tenants.

WE EXCEL AT WHAT WE DO - YOU CAN TRUST US